電源の不確定性を考慮した停電作業系統候補導出に関する研究―過酷潮流条件の検討―
電源の不確定性を考慮した停電作業系統候補導出に関する研究―過酷潮流条件の検討―
カテゴリ: 論文誌(論文単位)
グループ名: 【B】電力・エネルギー部門
発行日: 2022/06/01
タイトル(英語): A Deriving Method for System Configuration Candidates of Outage Works by Considering Uncertainty of Power Supply―A Study on Severe Power Flow Conditions―
著者名: 造賀 芳文(広島大学大学院先進理工系科学研究科),重光 紗英(広島大学大学院先進理工系科学研究科),川原 耕治(広島工業大学工学部電気システム工学科),森川 史也(広島大学大学院先進理工系科学研究科),餘利野 直人(広島大学大学院先進理工系科学研究科),佐々木 豊(広島大学大学院先進理工系科学研究科)
著者名(英語): Yoshifumi Zoka (Graduate School of Advanced Science and Engineering, Hiroshima University), Sae Shigemitsu (Graduate School of Advanced Science and Engineering, Hiroshima University), Koji Kawahara (Hiroshima Institute of Technology), Fumiya Morikawa (Graduate School of Advanced Science and Engineering, Hiroshima University), Naoto Yorino (Graduate School of Advanced Science and Engineering, Hiroshima University), Yutaka Sasaki (Graduate School of Advanced Science and Engineering, Hiroshima University)
キーワード: 停電作業計画,供給信頼度,太陽光発電,作業系統 outage work planning,power supply reliability,photovoltaic generation,working system configuration
要約(英語): Electric power system is one of the most important infrastructures and regular maintenance works (inspection, repair, replacement and so on) are very important tasks for transmission system operators (TSO). The maintenance work with partial outage is referred to as outage work” and the authors have so far studied a highly reliable outage work planning system for large scale power grids. In these days, however, a huge number of photovoltaic (PV) generation systems are being installed into the power grids. PV outputs are strongly affected by weather conditions and very difficult to be anticipated in advance. In addition, it is getting difficult for TSOs to grasp operation patterns of even traditional large-scale power sources due to the deregulation in the electricity industry. The planning task of annual outage work program is also getting difficult. The authors, therefore, believe that it is necessary to consider suitable supply-demand conditions for obtaining reliable grid configurations during outage works even in the uncertain circumstances. In this paper, the authors investigate what kind of conditions should be assumed for outage work planning and propose a deriving method to obtain appropriate grid configurations during outage works. The effectiveness of the proposed method is verified through several numerical simulations.
本誌: 電気学会論文誌B(電力・エネルギー部門誌) Vol.142 No.6 (2022)
本誌掲載ページ: 287-294 p
原稿種別: 論文/日本語
電子版へのリンク: https://www.jstage.jst.go.jp/article/ieejpes/142/6/142_287/_article/-char/ja/